Library Renovation Project
Phase Two Begins May 30, 2025
Please bear with us while we update and expand our facility to enhance your library experience.
.png)
Phases of Construction
1
Phase One
Feb-May 2025
Construction begins in the main part of the library and bathrooms. Library operations will continue with limited services in the Munnecke Room. Storytime and Book Club will relocate to Leland Community United Methodist Chruch at 106 4th St, Leland.

2
Phase Two
May-August 2025
The main part of the library will reopen. Phase two includes the addition of the new children's room on the south side of the building. More of our collection will be available. Sitework, including roofing and exterior painting will happen during Phase Two.
3
Phase Three
Sept-October 2025
The parking area and sidewalk, as well as renovations in the Munnecke Room will happen in Phase Three.